Tuesday, July 14, 2009

Whats New in PMBOK 4th Edition - Process Changes


There are 42 processes now insted of 44

Deleted Processes:

4.2 Develop Preliminary Scope Statement

5.1 Plan Scope

Changed Processes:

4.7 Close Project --> 4.6 Close Project or Phase

Manage Project Team [Controlling --> Executing]

10.4 Manage Stakeholders --> Manage Stakeholder Expectations. [Controlling --> Executing]

12.1 Plan Purchases and Acquisitions + 12.2 Plan Contracting = 12.1 Plan Procurements.

12.3 Request Seller Responses + 12.4 Select Sellers = 12.2 Conduct Procurements.

Added Processes
    5.1 Collect Requirements
      10.1 Identify Stakeholders